A homeowner asks for an extra outlet in the kitchen. The architect swaps a beam size. You open a wall and find rot nobody planned for. Each of these changes costs money and time, and without a signed change order, you may never get paid for it.

This free change order template gives you a simple, professional form to document every change before the work starts. It’s built for general contractors, remodelers and custom home builders, and it comes in three formats:

  • Word (.docx) – edit the layout, add your logo, print or email it.
  • Excel (.xlsx) – enter line items and the form adds up labor, materials, markup and the new contract total for you.
  • Fillable PDF – type straight into the form fields on any device and send it for signature.

Below, you'll find what goes into each section of the form, a filled-out example, and how to price and get changes approved without slowing the job down.

What is a change order?

A change order is a written agreement that changes the original construction contract. It records what work is being added, removed or modified, what it costs, and how it affects the schedule. Once both parties sign it, it becomes part of the contract.

Change orders usually come from four places:

SourceExample
Client requestThe homeowner upgrades from laminate to quartz countertops.
Design changeThe architect revises a window size after framing starts.
Unforeseen conditionsDemolition uncovers water damage or outdated wiring.
Code or permit requirementsThe inspector requires an extra smoke detector or egress window.

A change order is different from a change order request, which is only a proposal. It is also different from a construction change directive, which tells you to proceed before the price is agreed. This template works for both requests and final change orders: send it as a request, then have it signed once the price and schedule are agreed.

For the full change order process and management tips, see our guide on how to manage construction change orders.

What to include in a change order form

A good change order form answers five questions: what changed, why, how much, how long, and who agreed. Our template is split into eight sections that cover all of them.

#SectionWhat to fill inWhy it matters
1Company and change order detailsYour company name, license number, contact info, change order number and dateNumbering each change order in sequence (CO-001, CO-002) makes them easy to track and reference on invoices.
2Project informationProject name and address, client name, original contract date and number, project managerTies the change order to the right contract so there's no confusion later.
3Change detailsType of change, who requested it, a clear description of the work, the reason, and attached drawings or photosA vague description is the most common cause of change order disputes.
4Cost breakdownLine items for labor, materials, equipment and subcontractors, plus markup and taxShows the client how you reached the price, which speeds up approval.
5Schedule impactDays added or removed and the revised completion dateProtects you from delay claims when extra work pushes the finish date.
6Contract summaryOriginal contract sum, previous change orders, this change order, and the new contract sumGives both sides a running total so the final bill holds no surprises.
7Payment termsWhen the change order is billed (on approval, with the next progress invoice, or at completion)Settles when you get paid before the work starts.
8Approval and signaturesContractor and client names, signatures and datesMakes the change legally part of the contract. No signature, no work.

The contract summary in section 6 is the one most free forms leave out. It shows the client how each change adds up, which is often the moment they decide whether the next upgrade is worth it.

How to fill out the change order template (with an example)

Here's how the template looks when it's filled in for a real-world change. In this example, a homeowner on a $68,500 kitchen remodel asks to upgrade from laminate to quartz countertops and add three pendant lights over the island.

  1. Number and date the change order. This is the second change on the job, so it's CO-002, dated the day you send it.
  2. Fill in the project information. Copy the project name, address, client and original contract number from your contract.
  3. Describe the change in plain words. "Replace laminate countertops (42 sq ft) with 3 cm quartz, client-selected color. Supply and install three pendant lights over the island on a new dimmer switch." Mark the type as client request and attach the quartz quote and a lighting sketch.
  4. Price every line item. List each cost separately, and show credits for work you're no longer doing as negative amounts.
  5. Add markup and tax. Apply your overhead and profit markup to the subtotal. Add sales tax if your state taxes materials on this type of job.
  6. State the schedule impact. Countertop fabrication and electrical work add three working days.
  7. Update the contract summary. Add this change to the running total so the client sees the new contract sum.
  8. Set payment terms and get signatures. Both parties sign before any of the new work starts.

Example cost breakdown (CO-002)

DescriptionTypeQtyUnitUnit costAmount
Credit: laminate countertop allowanceMaterial1lump sum-$2,400-$2,400
Quartz countertops, fabricated and installedSubcontractor42sq ft$95$3,990
Pendant light fixturesMaterial3each$140$420
Electrician: wiring, dimmer, installLabor6hours$85$510
Drywall patch and paintLabor4hours$60$240
Subtotal$2,760
Overhead and profit (15%)$414
Sales tax (0% in this example)$0
Change order total$3,174

Example contract summary

LineAmount
Original contract sum$68,500
Net change from previous change orders (CO-001)$1,850
Contract sum before this change order$70,350
This change order (CO-002)$3,174
New contract sum$73,524

Schedule impact: +3 working days. Original completion: Friday, November 20, 2026. Revised completion: Wednesday, November 25, 2026.

Payment terms: 50% due on approval, balance billed with the next progress invoice.

The Excel version of the template does this math for you: enter quantities and unit costs, set your markup and tax rates, and the totals and new contract sum update on their own.

Tips for using your change order form

The rule that protects your margin is simple: no signed change order, no extra work. Every change follows the same path, and work only starts once the client has signed.

If the client pushes back on price or scope, revise the form and resend it. Work starts only after both signatures are on it.

Do:

  • Put the change order process in your contract. Spell out how changes are requested, priced and approved, your markup rate, and that verbal approvals don't count.
  • Send it the same day. The longer you wait, the more the details blur and the harder it is to get paid.
  • Be specific. Name materials, quantities, brands and locations. "Upgrade countertops" invites a dispute; "42 sq ft of 3 cm quartz, color Calacatta" doesn't.
  • Include every cost. Add the hidden ones: extra trips, dumpster fees, permit revisions, supervision time and equipment rental.
  • Show credits too. When a change removes work, credit it on the same form. Clients trust a price more when they see what they're no longer paying for.
  • Keep a change order log. Track every change order's number, status, amount and invoice status in one place.

Avoid:

  • Starting work on a handshake. A text or a quick "go ahead" on site is hard to enforce if the client later disputes the cost.
  • Forgetting the schedule. If extra work delays completion and the change order doesn't say so, you may be on the hook for the delay.
  • Leaving out markup. Pricing changes at cost means your overhead and profit pay for the extra work.
  • Losing track of approved changes at billing time. Approved change orders that never make it onto an invoice are lost revenue.

Manage change orders faster in Buildern

A template works well for a few changes a month. Once you're running several jobs at once, the paperwork adds up: forms to email, signatures to chase, totals to retype into budgets and invoices. Buildern's change order software handles the same steps in one place:

  • Create change orders in minutes with pricing, schedule impact and details pulled from your project.
  • Get digital approvals. Clients review, approve and e-sign through a secure link, without logging in to Buildern.
  • Update the schedule automatically when a change is approved.
  • Turn approved changes into POs and subcontracts, and track the related bills.
  • See invoicing status for every change order, so approved work never slips through billing.
  • Keep a full record of every change order, with timestamps, cost changes and approval logs.

Construction Management Software

The all-in-one platform for managing construction projects from start to finish.

  • Project management
  • Budget tracking
  • Estimates & proposals
  • Client communication
Book a Free Demo

No credit card required

Frequently Asked Questions

What is a change order form?

A change order form is a document that records a change to a construction contract: the work added or removed, its cost, its effect on the schedule, and the signatures of both parties approving it.

Who signs a change order?

At minimum, the contractor and the client (the property owner or the party who signed the original contract). On larger projects, the architect or lender may also need to sign. Check your contract for who has approval authority.

Is a change order legally binding?

Once both parties sign it, a change order generally becomes part of the original contract. Requirements vary by state and contract, so have your contract and change order language reviewed by a construction attorney.

What's the difference between a change order and a change order request?

A change order request proposes a change and its price. It becomes a change order once both parties agree and sign. You can use this template for both.

How much should I mark up a change order?

Many contractors apply the same overhead and profit markup they use on the original bid, often written into the contract. Whatever rate you use, state it in your contract so clients aren't surprised.

Can a change order reduce the contract price?

Yes. When the client removes work or picks a cheaper option, enter the credit as a negative line item. The contract summary will show the lower contract sum.

Should I use a template or software for change orders?

A template is a good fit for a few changes per project. If you manage several projects or many changes, software like Buildern saves time on approvals, budget updates and invoicing.