Angus Cowan has been building in Brisbane since 1999. For most of that time, he ran his business the way many builders still do: estimates in spreadsheets, projects managed in a separate tool, and a lot of late nights stitching the two together. Today, his estimating, scheduling, budgets, client invoices and files all live in one place. The result? A tighter, more efficient business, and a few free afternoons on the golf course.
| At a glance | |
|---|---|
| Company | Angus Cowan Constructions |
| Location | Brisbane, Queensland, Australia |
| Founded | 1999 |
| Specialty | Large Queenslander renovations and restorations, plus select architectural new homes |
| Most-used Buildern tools | Estimating, takeoff, scheduling, budgets, Xero integration, client portal, timesheets, files |
| Key result | Same project quality and steady turnover with far fewer working hours |
About Angus Cowan Constructions
Angus started Angus Cowan Constructions straight out of his carpentry apprenticeship in 1999. He began with small residential jobs, a couple of apprentices and his own two hands. As the projects grew, so did the team. Over the years he has trained 15 or 16 apprentice carpenters, and today the crew includes six tradesmen, two apprentices and one admin staff member.
The company has carved out a clear niche: large renovations and restorations of Queenslanders, the classic timber homes native to Brisbane and regional Queensland. Many of these houses are 100 to 150 years old. The team also builds a few architectural new homes, but stays focused. “We’re sitting in our own little niche segment with the Queenslanders, and it works for us,” he says.
On a typical day, Angus visits two or three sites from 6:30 a.m., then spends the afternoon in the office on clients, suppliers and estimating. He prices every job himself.
The challenge: one job, too many tools
In the early days, everything ran on pen and paper. Over time Angus moved to spreadsheets, then to a spreadsheet-based estimating program he used for close to ten years. Later, he paired a dedicated estimating tool with a separate project management platform.
Each tool did its part. None of them did the whole job. “The hardest thing was to estimate a project, but then you had to siphon all of the data and information out of that, inject it into a proposal, and then use the proposal to actually manage the project,” Angus explains. “It was just very clunky. There were different softwares for different parts of the puzzle, but nothing that would do the whole lot.”
So Angus went looking. Over roughly two years, he reviewed somewhere between 15 and 20 platforms. Some were built for large commercial contractors. Some were too basic for a business running multi-million-dollar renovations, with simple schedules and thin estimating. Others were hard to navigate. A few US-based tools showed little interest in supporting Australian builders at all.
Why Buildern stood out
Angus was one of Buildern’s early adopters, and the first thing that won him over was the interface. Estimating, scheduling, variations and the rest are laid out as clear modules, in the same order a builder actually runs a project.
“Software has to be easy to use. A lot of these softwares have probably got good stuff, good guts, but it’s all buried and you can’t find where you’re going. When I stumbled on Buildern, the interface was the first thing that grabbed my attention.”
Just as important, Buildern is built for builders in any country. For an Australian firm that had been turned away by tools focused only on the US market, that mattered.
How Angus uses Buildern every day
Estimating and takeoff: the heart of the business
Angus credits careful estimating for a record most builders would envy. “Not one project in 26 years have we gone backwards on or lost money,” he says. He has seen outsourced estimators come back with a $1.25 million figure on a job he priced at around $2 million. “If I was to even entertain that, I would be broke within weeks.”
Inside Buildern, he has built detailed estimating templates for each type of work: a Queenslander renovation, a new architectural home, or a small pool house. He simply pulls the right one forward and adjusts. “The estimating tool is excellent,” he says, “which links with the takeoff as well.” He also rates the takeoff for being powerful without being complicated: “Some takeoffs, you nearly need a degree to drive it.”
Scheduling with baselines and critical path
“I can’t fault the schedule,” Angus says. He switches between daily, weekly and yearly views, and relies on two features in particular. Every two weeks or so, he saves a baseline. Months later, he can compare against it to see whether the job is speeding up or slipping. “It’s a two-second thing to do,” he notes. The critical path keeps the key dependencies in view.
Budgets, invoices and Xero
The budget is how Angus tracks every project’s health. Buildern’s integration with Xero, which he estimates about 95% of Australian builders use, means his financials stay in sync. “It integrates beautifully. It’s never been clunky,” he says. Client invoices and variations are documented clearly, which makes it easier to stay on top of cash flow.
A client portal with the right level of access
Angus learned that sharing everything with clients can backfire. Buildern lets him choose exactly what each client sees, typically the schedule, variations and invoices. “You want to be professional and let your client into your system a bit so they have trust in you,” he explains. “But sometimes less is more.”
Timesheets and files
The crew now logs time from their phones through Buildern’s timesheets. Every new job also starts from a file template, with folders, neighbour notification letters and to-do lists ready to go, so everyone knows exactly where to look.
The results: efficiency, and time back
For Angus, the biggest gain is efficiency. Well-documented variations and on-time client invoices keep the financial side on track too.
“Everyone in my team knows where to look for everything. You’ve got to have your own systems as a builder and business owner anyway, but Buildern helps implement those systems and keep them neat and tidy.”
Now in his fifties, Angus isn’t chasing growth at any cost. A few years ago he was at the peak of his building career, but working “mad hours” to get there. Today, turnover is only slightly lower, right where he wants it, and his working hours have dropped dramatically.
“It’s been a godsend for me. I can sneak off on a Friday afternoon and even a Wednesday afternoon. I love playing golf. So Buildern has let me play golf.”
Angus’s advice to other builders
Angus still talks to plenty of builders, young and experienced, who run their businesses on pen, paper and spreadsheets. His advice is simple: “Have a go, try it, persist, because the results are well worth it.”
He recommends leaning on Buildern’s onboarding team while you set things up. The learning curve pays off quickly, because once your templates and systems are in place, every new job becomes “rinse and repeat.” On pen and paper, every job starts from scratch.
Ready to spend less time on admin and more time on what you love? Book a Buildern demo and see how estimating, scheduling and financials work together in one platform.