{"id":6625,"date":"2026-11-27T06:05:21","date_gmt":"2026-11-27T14:05:21","guid":{"rendered":"https:\/\/buildern.com\/resources\/?p=6625"},"modified":"2026-11-27T06:05:22","modified_gmt":"2026-11-27T14:05:22","slug":"time-and-materials-contract","status":"publish","type":"post","link":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/","title":{"rendered":"Time and Materials Contracts: A Builder&#8217;s Guide to Rates, Markup and NTE Caps"},"content":{"rendered":"\n<p class=\"wp-block-paragraph\">A time and materials (T&amp;M) contract lets you bill the client for the hours your crew actually works at an agreed hourly rate, plus the materials you actually use with an agreed markup. You don&#8217;t commit to a total price up front, so the client carries the risk of the job growing and you&#8217;re paid for the work you do.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">That sounds like a safe deal for a builder, and often it is. But T&amp;M only protects your margin if your hourly rates already include burden, overhead and profit, your markup covers handling and waste, and your paperwork holds up when the client questions an invoice. This guide covers when T&amp;M fits, how to set the numbers, how not-to-exceed caps shift the risk back toward you, and how T&amp;M compares to <a href=\"https:\/\/buildern.com\/resources\/blog\/cost-plus-contract\/\">cost-plus<\/a> and fixed-price work.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">What is a time and materials contract?<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">A time and materials contract is a construction agreement where the price is calculated from three parts:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Time:<\/strong> hours worked by each trade or role, billed at a fixed hourly rate set in the contract (for example, carpenter $85\/hr, laborer $55\/hr).<\/li>\n\n\n\n<li><strong>Materials:<\/strong> what you buy for the job, billed at cost plus a stated markup (for example, cost + 15%).<\/li>\n\n\n\n<li><strong>Other direct costs:<\/strong> equipment rental, dumpsters, permits and subcontractors, billed at cost plus a markup, or at set rates.<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">The key difference from other contract types is where your profit sits. In a T&amp;M contract, overhead and profit are built into the hourly rate and the markup. There&#8217;s no separate fee line.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">You bill on a set cycle, usually weekly or every two weeks, with timesheets and receipts to back each invoice. The final contract price isn&#8217;t known until the work is done, unless the contract sets a not-to-exceed cap.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">When a T&amp;M contract makes sense for a builder<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">T&amp;M fits when you can&#8217;t price the scope with confidence before the work starts. If you&#8217;d have to pad a fixed bid by 20\u201330% to feel safe, T&amp;M is usually fairer to both sides.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Good fits:<\/strong><\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Remodels and renovations with hidden conditions.<\/strong> You don&#8217;t know what&#8217;s behind the drywall or under the floor until you open it up.<\/li>\n\n\n\n<li><strong>Repair, insurance and restoration work.<\/strong> Water, fire and storm damage often grows once demolition starts.<\/li>\n\n\n\n<li><strong>Small jobs and service calls.<\/strong> A full estimate costs more time than the job is worth.<\/li>\n\n\n\n<li><strong>Work before the design is finished.<\/strong> Exploratory demo, early site work or a client who wants to start while plans are still changing.<\/li>\n\n\n\n<li><strong>Extra work on a fixed-price job.<\/strong> Many builders price unclear <a href=\"https:\/\/buildern.com\/resources\/blog\/construction-change-orders\/\">change orders<\/a> on T&amp;M when the client can&#8217;t wait for a firm quote.<\/li>\n\n\n\n<li><strong>Repeat clients who trust you.<\/strong> Property managers and investors who want speed over a locked price.<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Poor fits:<\/strong><\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>New custom homes with complete plans.<\/strong> The scope is defined, and most clients want a fixed price or a cost-plus contract with a guaranteed maximum price.<\/li>\n\n\n\n<li><strong>Clients on a tight, fixed budget.<\/strong> Open-ended billing creates stress and payment disputes.<\/li>\n\n\n\n<li><strong>Lender-financed projects.<\/strong> Construction lenders usually want a fixed contract sum or a GMP to size the loan and the draw schedule.<\/li>\n\n\n\n<li><strong>Jobs where you can&#8217;t track time well.<\/strong> If your crews don&#8217;t log hours by job and task, you can&#8217;t defend a T&amp;M invoice.<\/li>\n<\/ul>\n\n\n\n<h3 class=\"wp-block-heading\">The trade-off for the builder<\/h3>\n\n\n\n<figure class=\"wp-block-table\"><table class=\"has-fixed-layout\"><tbody><tr><th><\/th><th>What you gain<\/th><th>What you give up<\/th><\/tr><tr><td>Risk<\/td><td>Unknown conditions are paid for, not absorbed<\/td><td>Less upside: finishing early earns less, not more<\/td><\/tr><tr><td>Margin<\/td><td>Profit is locked into every hour and every purchase<\/td><td>No room to earn extra margin from efficiency<\/td><\/tr><tr><td>Admin<\/td><td>Quick to start, no detailed bid needed<\/td><td>Daily timesheets, receipts and more invoice questions<\/td><\/tr><tr><td>Client<\/td><td>Clear, line-by-line billing<\/td><td>Client may watch hours closely and challenge them<\/td><\/tr><\/tbody><\/table><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\">How to set T&amp;M labor rates<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Your T&amp;M hourly rate must cover four things: the worker&#8217;s wage, the labor burden on that wage, the hours you pay for but can&#8217;t bill, and a share of company overhead. Profit goes on top. Most builders who lose money on T&amp;M set the rate at &#8220;wage plus a bit&#8221; and miss two or three of these.<\/p>\n\n\n\n<ol class=\"wp-block-list\">\n<li><strong>Start with the base wage.<\/strong> Use the actual hourly pay for each role, not an average across the crew.<\/li>\n\n\n\n<li><strong>Add labor burden.<\/strong> Payroll taxes, workers&#8217; comp, general liability tied to payroll, health insurance, retirement, paid time off. For small residential builders this is often 25\u201340% of wages, and workers&#8217; comp varies a lot by trade and state. Our guide to labor burden walks through the calculation.<\/li>\n\n\n\n<li><strong>Adjust for non-billable time.<\/strong> Drive time between jobs, shop days, weather days, cleanup and training are paid but rarely billed. Divide the burdened cost by the share of paid hours you can bill.<\/li>\n\n\n\n<li><strong>Add overhead per billable hour.<\/strong> Divide your yearly overhead (office, vehicles, software, insurance, owner and admin salaries) by the billable field hours you expect in a year. See <a href=\"https:\/\/buildern.com\/resources\/blog\/typical-contractor-overhead-and-profit\/\">contractor overhead and profit<\/a> for what belongs in overhead.<\/li>\n\n\n\n<li><strong>Add profit as a margin on price.<\/strong> Divide the full cost by (1 \u2212 target margin), not cost \u00d7 (1 + margin).<\/li>\n<\/ol>\n\n\n\n<pre class=\"wp-block-code\"><code>\\text{T\\&amp;M rate} = \\dfrac{\\dfrac{\\text{wage} \\times (1 + \\text{burden \\%})}{\\text{billable share}} + \\text{overhead per billable hour}}{1 - \\text{profit margin}}<\/code><\/pre>\n\n\n\n<h3 class=\"wp-block-heading\">Worked example: lead carpenter<\/h3>\n\n\n\n<figure class=\"wp-block-table\"><table class=\"has-fixed-layout\"><tbody><tr><th>Step<\/th><th>Calculation<\/th><th>Result<\/th><\/tr><tr><td>Base wage<\/td><td><\/td><td>$35.00\/hr<\/td><\/tr><tr><td>+ Labor burden (30%)<\/td><td>$35.00 \u00d7 1.30<\/td><td>$45.50\/hr<\/td><\/tr><tr><td>\u00f7 Billable share (80%)<\/td><td>$45.50 \u00f7 0.80<\/td><td>$56.88\/hr<\/td><\/tr><tr><td>+ Overhead<\/td><td>$180,000 overhead \u00f7 9,000 billable hrs\/yr<\/td><td>+$20.00\/hr<\/td><\/tr><tr><td>= Full cost per billable hour<\/td><td><\/td><td>$76.88\/hr<\/td><\/tr><tr><td>\u00f7 (1 \u2212 12% profit margin)<\/td><td>$76.88 \u00f7 0.88<\/td><td>$87.36\/hr<\/td><\/tr><tr><td><strong>Billing rate (rounded)<\/strong><\/td><td><\/td><td><strong>$88\/hr<\/strong><\/td><\/tr><\/tbody><\/table><\/figure>\n\n\n\n<p class=\"wp-block-paragraph\">At $50\/hr, which looks like a healthy 43% over wage, this builder would lose about $27 on every billable hour. The wage is only 40% of the real billing rate.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Rate sheet tips<\/h3>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Set a rate per role,<\/strong> not one blended rate: owner or PM, site supervisor, lead carpenter, carpenter, laborer, and any in-house trades.<\/li>\n\n\n\n<li><strong>State overtime and after-hours rates<\/strong> (often 1.5\u00d7 for overtime and weekends) and when they apply, such as client-requested schedule changes.<\/li>\n\n\n\n<li><strong>Say how supervision and PM time are billed.<\/strong> Either bill them as hours or build them into the trade rates. Don&#8217;t leave it open.<\/li>\n\n\n\n<li><strong>Define billable time:<\/strong> travel to the site, material pickups, cleanup and minimum charges (for example, a 2-hour minimum per visit).<\/li>\n\n\n\n<li><strong>Add a rate review clause<\/strong> for jobs that run longer than 6\u201312 months, so wage increases can pass through.<\/li>\n<\/ul>\n\n\n\n<h2 class=\"wp-block-heading\">How to set material markup (and bill equipment and subs)<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Material markup on T&amp;M jobs commonly falls between 10% and 20%, with higher rates on small orders and lower rates on big-ticket items. The markup isn&#8217;t free profit. It pays for the time spent pricing, ordering, picking up, storing and returning materials, the cash you float until the client pays, and the waste and breakage you can&#8217;t bill item by item.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Keep markup and margin straight. A 15% markup on cost is about a 13% margin on the billed price ($100 cost \u00d7 1.15 = $115; $15 \u00f7 $115 = 13%). If you planned your numbers around a 15% margin, you need roughly an 18% markup.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">What to spell out for each cost type<\/h3>\n\n\n\n<figure class=\"wp-block-table\"><table class=\"has-fixed-layout\"><tbody><tr><th>Cost type<\/th><th>Typical billing method<\/th><th>Common markup range<\/th><th>Write into the contract<\/th><\/tr><tr><td>Materials<\/td><td>Supplier cost + markup<\/td><td>10\u201320%<\/td><td>Whether trade discounts and rebates pass to the client; who owns leftover material<\/td><\/tr><tr><td>Small tools and consumables<\/td><td>Flat % of labor or cost + markup<\/td><td>2\u20135% of labor, or included in rate<\/td><td>One method, so you don&#8217;t bill fasteners line by line<\/td><\/tr><tr><td>Owned equipment<\/td><td>Hourly or daily rate sheet<\/td><td>Rate includes ownership and upkeep<\/td><td>Rates per machine, minimum charges, operator billed separately or not<\/td><\/tr><tr><td>Rented equipment<\/td><td>Rental invoice + markup<\/td><td>10\u201315%<\/td><td>Fuel, delivery and damage waiver billed at cost<\/td><\/tr><tr><td>Subcontractors<\/td><td>Sub invoice + markup<\/td><td>5\u201315%<\/td><td>Whether subs bill you lump sum or T&amp;M; your markup applies either way<\/td><\/tr><tr><td>Permits, fees, dumpsters<\/td><td>At cost, or cost + small markup<\/td><td>0\u201310%<\/td><td>List them so they aren&#8217;t a surprise<\/td><\/tr><\/tbody><\/table><\/figure>\n\n\n\n<p class=\"wp-block-paragraph\">Ranges are typical residential figures, not rules. Your markup should come from your own overhead and the admin each cost type creates.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Common mistakes<\/h3>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Billing materials at retail price instead of your cost.<\/strong> If the contract says cost plus markup, you must bill your actual cost, net of discounts unless the contract says otherwise.<\/li>\n\n\n\n<li><strong>Forgetting delivery, sales tax and restocking fees.<\/strong> Bill them as part of material cost.<\/li>\n\n\n\n<li><strong>Marking up the same cost twice.<\/strong> If a sub&#8217;s invoice already includes their materials with a markup, your markup applies to the sub line, not again to the materials inside it.<\/li>\n\n\n\n<li><strong>No rule for leftovers.<\/strong> Say whether surplus material goes to the client, gets returned for credit or stays with you.<\/li>\n<\/ul>\n\n\n\n<h2 class=\"wp-block-heading\">Not-to-exceed caps: how they work and how to protect yourself<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">A not-to-exceed (NTE) cap sets the most the client will pay for the defined scope. You bill actual time and materials up to the cap, and any cost above it is yours unless a change order raises it. Clients like NTE because it removes the open-ended feeling of T&amp;M. For you, it brings back fixed-price risk with none of the fixed-price upside: if the job comes in under the cap, the client keeps the savings.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">That doesn&#8217;t mean you should refuse a cap. It means a cap needs the same care as a bid.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">How to set and manage an NTE cap<\/h3>\n\n\n\n<ol class=\"wp-block-list\">\n<li><strong>Estimate the scope as if it were a fixed bid,<\/strong> then add a contingency for the unknowns that made you choose T&amp;M in the first place. A cap set at your best-case estimate is a loss waiting to happen.<\/li>\n\n\n\n<li><strong>Tie the cap to a written scope.<\/strong> List what&#8217;s included and what&#8217;s excluded. Work outside that list is a change, not part of the cap.<\/li>\n\n\n\n<li><strong>Name the conditions that adjust the cap:<\/strong> hidden damage, code-required upgrades, client changes, material price jumps over a set percentage, and delays the client causes.<\/li>\n\n\n\n<li><strong>Set warning points.<\/strong> Commit to notify the client in writing when billed costs reach about 75% of the cap, with a forecast of the final cost. This gives both sides time to cut scope or approve more money.<\/li>\n\n\n\n<li><strong>Stop and get approval before you cross the cap.<\/strong> Make it a contract rule that work beyond the cap needs a signed change order. Without that, the client can refuse to pay for work done after the limit.<\/li>\n\n\n\n<li><strong>Track cost against the cap weekly,<\/strong> not at the end of the job. A cap is only useful if you know how close you are.<\/li>\n<\/ol>\n\n\n\n<h3 class=\"wp-block-heading\">NTE cap vs. guaranteed maximum price<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">An NTE cap on a T&amp;M job works much like a guaranteed maximum price (GMP) on a cost-plus job: both limit what the client pays and push overruns to the builder. The differences are in how your profit is calculated and whether savings are shared.<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>NTE (T&amp;M):<\/strong> profit is inside the rates and markup, so you earn it on every billed hour until the cap. Savings under the cap usually go fully to the client.<\/li>\n\n\n\n<li><strong>GMP (cost-plus):<\/strong> costs are passed through and your fee is separate. GMP contracts often include a shared savings clause that splits any savings between builder and client.<\/li>\n<\/ul>\n\n\n\n<h2 class=\"wp-block-heading\">T&amp;M vs. cost-plus vs. fixed price<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">T&amp;M and cost-plus both bill the client for actual costs, and the line between them is often blurry. The practical difference is where your profit lives. In T&amp;M, profit is baked into the hourly rates and markup. In cost-plus, labor and materials pass through at actual cost and your profit comes from a separate fee. Fixed price puts all cost risk on you in exchange for keeping any savings.<\/p>\n\n\n\n<figure class=\"wp-block-table\"><table class=\"has-fixed-layout\"><tbody><tr><th><\/th><th>Time and materials<\/th><th>Cost-plus<\/th><th>Fixed price (lump sum)<\/th><\/tr><tr><td>How the price is set<\/td><td>Hours \u00d7 agreed rates + materials \u00d7 markup<\/td><td>Actual costs + a fee (% or fixed)<\/td><td>One agreed total before work starts<\/td><\/tr><tr><td>Where profit sits<\/td><td>Inside the hourly rates and markup<\/td><td>In the separate fee<\/td><td>In the gap between price and your actual cost<\/td><\/tr><tr><td>Labor billed at<\/td><td>Set billing rate (e.g. $88\/hr)<\/td><td>Actual payroll cost incl. burden<\/td><td>Not itemized<\/td><\/tr><tr><td>Cost-overrun risk<\/td><td>Client (unless NTE cap)<\/td><td>Client (unless GMP)<\/td><td>Builder<\/td><\/tr><tr><td>Savings from efficiency<\/td><td>Client (fewer hours billed)<\/td><td>Client, or shared under a GMP<\/td><td>Builder<\/td><\/tr><tr><td>Client sees<\/td><td>Timesheets, receipts, rate sheet<\/td><td>Full books: payroll, invoices, fee<\/td><td>Progress against milestones<\/td><\/tr><tr><td>Admin load<\/td><td>High<\/td><td>Highest<\/td><td>Lowest during the job, highest at bid time<\/td><\/tr><tr><td>Best for<\/td><td>Small jobs, repairs, unclear remodels, change orders<\/td><td>Custom homes, high-end builds with open selections<\/td><td>Clear plans and specs, competitive bids, lender-financed work<\/td><\/tr><\/tbody><\/table><\/figure>\n\n\n\n<h3 class=\"wp-block-heading\">How to choose<\/h3>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>The scope is clear and drawings are complete:<\/strong> fixed price. You earn more by running the job well.<\/li>\n\n\n\n<li><strong>The scope is mostly clear, but selections and allowances are open:<\/strong> cost-plus, often with a GMP. The client gets open books and you get a protected fee.<\/li>\n\n\n\n<li><strong>The scope is unclear, small or likely to change daily:<\/strong> T&amp;M, with an NTE cap if the client needs a budget limit.<\/li>\n\n\n\n<li><strong>A fixed-price job runs into unknown work:<\/strong> price that change order on T&amp;M at your contract rates rather than guessing a lump sum.<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">Many builders mix the three on one project: a fixed price for the main scope, allowances for selections, and T&amp;M for hidden conditions and client changes. Our comparison of <a href=\"https:\/\/buildern.com\/resources\/blog\/cost-plus-fixed-price\/\">cost-plus vs. fixed-price contracts<\/a> goes deeper on those two, and design-build vs. design-bid-build covers how delivery method affects which contract you&#8217;ll be offered.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">Example: a weekly T&amp;M invoice<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">A builder is repairing water damage in a bathroom and the subfloor below it. The contract uses a rate sheet built with the method above, a 15% material markup, 10% on subs and rentals, weekly billing and a $40,000 NTE cap. This is week 2.<\/p>\n\n\n\n<figure class=\"wp-block-table\"><table class=\"has-fixed-layout\"><tbody><tr><th>Line<\/th><th>Quantity<\/th><th>Rate<\/th><th>Amount<\/th><\/tr><tr><td>Lead carpenter<\/td><td>32 hrs<\/td><td>$88\/hr<\/td><td>$2,816<\/td><\/tr><tr><td>Carpenter<\/td><td>32 hrs<\/td><td>$72\/hr<\/td><td>$2,304<\/td><\/tr><tr><td>Laborer<\/td><td>16 hrs<\/td><td>$52\/hr<\/td><td>$832<\/td><\/tr><tr><td><strong>Labor subtotal<\/strong><\/td><td><\/td><td><\/td><td><strong>$5,952<\/strong><\/td><\/tr><tr><td>Materials (receipts attached)<\/td><td>$3,400 cost<\/td><td>+ 15%<\/td><td>$3,910<\/td><\/tr><tr><td>Dumpster rental<\/td><td>$450 cost<\/td><td>+ 10%<\/td><td>$495<\/td><\/tr><tr><td>Plumbing sub (invoice attached)<\/td><td>$1,800 cost<\/td><td>+ 10%<\/td><td>$1,980<\/td><\/tr><tr><td><strong>Invoice total, week 2<\/strong><\/td><td><\/td><td><\/td><td><strong>$12,337<\/strong><\/td><\/tr><tr><td>Billed in week 1<\/td><td><\/td><td><\/td><td>$14,200<\/td><\/tr><tr><td><strong>Billed to date<\/strong><\/td><td><\/td><td><\/td><td><strong>$26,537 (66% of the $40,000 cap)<\/strong><\/td><\/tr><\/tbody><\/table><\/figure>\n\n\n\n<p class=\"wp-block-paragraph\">What makes this invoice easy to approve: hours tie to signed daily timesheets, every cost line has a receipt or sub invoice, the rates match the contract&#8217;s rate sheet, and the running total against the cap is on the invoice. With 66% of the cap used and the tile work still ahead, the builder should send the client a cost forecast now, before the 75% warning point.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">What to put in a T&amp;M contract<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Most T&amp;M disputes come from what the contract left out, not from the rates. Before the client signs, make sure the contract covers:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Scope description,<\/strong> even if it&#8217;s loose, plus what&#8217;s excluded<\/li>\n\n\n\n<li><strong>Labor rate sheet<\/strong> by role, with overtime, weekend and after-hours rates<\/li>\n\n\n\n<li><strong>What counts as billable time:<\/strong> travel, pickups, cleanup, supervision, minimum charges<\/li>\n\n\n\n<li><strong>Material markup<\/strong> and whether discounts, rebates and leftovers go to the client<\/li>\n\n\n\n<li><strong>Equipment rates<\/strong> for owned equipment and markup on rentals<\/li>\n\n\n\n<li><strong>Subcontractor markup<\/strong> and how sub work is documented<\/li>\n\n\n\n<li><strong>NTE cap<\/strong> (if any), what adjusts it, the warning point and the stop-and-approve rule<\/li>\n\n\n\n<li><strong>Documentation the client gets:<\/strong> daily or weekly timesheets, receipts, sub invoices<\/li>\n\n\n\n<li><strong>Billing cycle and payment terms,<\/strong> for example weekly invoices due in 7 days, and late-payment terms<\/li>\n\n\n\n<li><strong>How changes are handled:<\/strong> written change orders for scope beyond the original description<\/li>\n\n\n\n<li><strong>Deposit or retainer,<\/strong> if you need one to cover early material buys<\/li>\n\n\n\n<li><strong>Client&#8217;s right to review records<\/strong> and how long they have to dispute an invoice<\/li>\n\n\n\n<li><strong>Rate review clause<\/strong> for long jobs<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">Have a local construction attorney review your T&amp;M template once. Lien rights, deposit limits and home-improvement contract rules vary by state.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">How to track and bill T&amp;M work without disputes<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">A T&amp;M invoice is only as strong as the records behind it. Clients rarely question the rate they agreed to. They question the hours.<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Log time daily, by job and task.<\/strong> Hours written up at the end of the week are hard to defend. Mobile time tracking with GPS or photos gives the client confidence.<\/li>\n\n\n\n<li><strong>Get daily or weekly sign-off.<\/strong> A client or site rep initialing timesheets each week turns most disputes into non-issues.<\/li>\n\n\n\n<li><strong>Tie every receipt to the job right away.<\/strong> Snap a photo at the counter and code it to the job before the paper gets lost.<\/li>\n\n\n\n<li><strong>Watch cost against the cap or budget every week.<\/strong> If you&#8217;re tracking an NTE, compare billed-to-date with the cap and forecast what&#8217;s left.<\/li>\n\n\n\n<li><strong>Keep the invoice format the same every cycle:<\/strong> labor by role, materials, equipment, subs, then totals and the running balance.<\/li>\n\n\n\n<li><strong>Compare actual cost to billed amount.<\/strong> <a href=\"https:\/\/buildern.com\/resources\/blog\/job-costing-in-construction\/\">Job costing<\/a> shows whether your rates and markup are earning what you planned. If they aren&#8217;t, fix the rate sheet before the next job.<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">Construction management software like Buildern brings these steps into one place: crews log time by job from their phones, receipts and purchase orders post to the job budget, and T&amp;M invoices pull hours and costs straight from those records. You can see billed-to-date against the cap at any time instead of rebuilding it from spreadsheets.<\/p>\n\n\n\n<section class=\"wp-block-buildern-article-banner article-banner article-banner--general\"><div class=\"article-banner__general-layout\"><div class=\"article-banner__icons\"><img class=\"article-banner__icon\" src=\"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/10\/export.svg\" alt=\"\" aria-hidden=\"true\" loading=\"lazy\" decoding=\"async\"\/><img class=\"article-banner__icon\" src=\"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/10\/Group-155090.svg\" alt=\"\" aria-hidden=\"true\" loading=\"lazy\" decoding=\"async\"\/><\/div><div class=\"article-banner__content\"><img class=\"article-banner__logo\" src=\"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/10\/Buildern-Logo-Colored-100.svg\" alt=\"Buildern\" loading=\"lazy\" decoding=\"async\"\/><h3 class=\"article-banner__heading\">Construction Management Software<\/h3><p class=\"article-banner__description\">The all-in-one platform for managing construction projects from start to finish.<\/p><ul class=\"article-banner__checklist\"><li class=\"article-banner__checklist-item\"><span class=\"article-banner__check\" aria-hidden=\"true\"><\/span><span class=\"article-banner__checklist-label\">Project management<\/span><\/li><li class=\"article-banner__checklist-item\"><span class=\"article-banner__check\" aria-hidden=\"true\"><\/span><span class=\"article-banner__checklist-label\">Budget tracking<\/span><\/li><li class=\"article-banner__checklist-item\"><span class=\"article-banner__check\" aria-hidden=\"true\"><\/span><span class=\"article-banner__checklist-label\">Estimates &amp; proposals<\/span><\/li><li class=\"article-banner__checklist-item\"><span class=\"article-banner__check\" aria-hidden=\"true\"><\/span><span class=\"article-banner__checklist-label\">Client communication<\/span><\/li><\/ul><a class=\"article-banner__button\" href=\"https:\/\/app.buildern.com\/signup\">Book a Free Demo<\/a><p class=\"article-banner__footnote\">No credit card required<\/p><\/div><\/div><\/section>\n\n\n\n<section class=\"wp-block-buildern-article-faq article-faq\" data-article-faq=\"\"><h2 class=\"article-faq__title\">Frequently Asked Questions<\/h2><div class=\"article-faq__items\">\n<details class=\"wp-block-buildern-article-faq-item article-faq__item\"><summary class=\"article-faq__question\"><h4 class=\"article-faq__question-title\">What is a time and materials contract in construction?<\/h4><span class=\"article-faq__chevron\" aria-hidden=\"true\"><svg width=\"12\" height=\"8\" viewBox=\"0 0 12 8\" fill=\"none\" focusable=\"false\" aria-hidden=\"true\"><path d=\"M1 1.5L6 6.5L11 1.5\" stroke=\"currentColor\" stroke-width=\"1.5\" stroke-linecap=\"round\" stroke-linejoin=\"round\"><\/path><\/svg><\/span><\/summary><div class=\"article-faq__answer\">\n<p class=\"wp-block-paragraph\">It&#8217;s a contract where the client pays for the labor hours worked at agreed hourly rates, plus materials and other direct costs at cost plus an agreed markup. The total price isn&#8217;t fixed in advance unless the contract includes a not-to-exceed cap.<\/p>\n<\/div><\/details>\n\n\n\n<details class=\"wp-block-buildern-article-faq-item article-faq__item\"><summary class=\"article-faq__question\"><h4 class=\"article-faq__question-title\">What is a typical markup on a time and materials contract?<\/h4><span class=\"article-faq__chevron\" aria-hidden=\"true\"><svg width=\"12\" height=\"8\" viewBox=\"0 0 12 8\" fill=\"none\" focusable=\"false\" aria-hidden=\"true\"><path d=\"M1 1.5L6 6.5L11 1.5\" stroke=\"currentColor\" stroke-width=\"1.5\" stroke-linecap=\"round\" stroke-linejoin=\"round\"><\/path><\/svg><\/span><\/summary><div class=\"article-faq__answer\">\n<p class=\"wp-block-paragraph\">Material markups of 10\u201320% are common for residential builders, with 5\u201315% on subcontractors and 10\u201315% on rented equipment. Your own overhead should set the number, not a rule of thumb. Remember that markup is not the same as margin: a 15% markup is about a 13% margin.<\/p>\n<\/div><\/details>\n\n\n\n<details class=\"wp-block-buildern-article-faq-item article-faq__item\"><summary class=\"article-faq__question\"><h4 class=\"article-faq__question-title\">How do I calculate a T&amp;M labor rate?<\/h4><span class=\"article-faq__chevron\" aria-hidden=\"true\"><svg width=\"12\" height=\"8\" viewBox=\"0 0 12 8\" fill=\"none\" focusable=\"false\" aria-hidden=\"true\"><path d=\"M1 1.5L6 6.5L11 1.5\" stroke=\"currentColor\" stroke-width=\"1.5\" stroke-linecap=\"round\" stroke-linejoin=\"round\"><\/path><\/svg><\/span><\/summary><div class=\"article-faq__answer\">\n<p class=\"wp-block-paragraph\">Take the base wage, add labor burden, divide by the share of paid hours you can bill, add overhead per billable hour, then divide by (1 \u2212 your profit margin). In the example above, a $35\/hr carpenter becomes an $88\/hr billing rate.<\/p>\n<\/div><\/details>\n\n\n\n<details class=\"wp-block-buildern-article-faq-item article-faq__item\"><summary class=\"article-faq__question\"><h4 class=\"article-faq__question-title\">What is a not-to-exceed clause?<\/h4><span class=\"article-faq__chevron\" aria-hidden=\"true\"><svg width=\"12\" height=\"8\" viewBox=\"0 0 12 8\" fill=\"none\" focusable=\"false\" aria-hidden=\"true\"><path d=\"M1 1.5L6 6.5L11 1.5\" stroke=\"currentColor\" stroke-width=\"1.5\" stroke-linecap=\"round\" stroke-linejoin=\"round\"><\/path><\/svg><\/span><\/summary><div class=\"article-faq__answer\">\n<p class=\"wp-block-paragraph\">A not-to-exceed clause caps the total the client will pay for a defined scope. You bill actual time and materials up to the cap, and costs above it fall on you unless a change order raises the cap.<\/p>\n<\/div><\/details>\n\n\n\n<details class=\"wp-block-buildern-article-faq-item article-faq__item\"><summary class=\"article-faq__question\"><h4 class=\"article-faq__question-title\">What&#8217;s the difference between T&amp;M and cost-plus?<\/h4><span class=\"article-faq__chevron\" aria-hidden=\"true\"><svg width=\"12\" height=\"8\" viewBox=\"0 0 12 8\" fill=\"none\" focusable=\"false\" aria-hidden=\"true\"><path d=\"M1 1.5L6 6.5L11 1.5\" stroke=\"currentColor\" stroke-width=\"1.5\" stroke-linecap=\"round\" stroke-linejoin=\"round\"><\/path><\/svg><\/span><\/summary><div class=\"article-faq__answer\">\n<p class=\"wp-block-paragraph\">Both bill actual costs. In T&amp;M, profit is built into the hourly rates and material markup. In cost-plus, labor and materials pass through at actual cost and the builder earns a separate fee, usually a percentage or a fixed amount.<\/p>\n<\/div><\/details>\n\n\n\n<details class=\"wp-block-buildern-article-faq-item article-faq__item\"><summary class=\"article-faq__question\"><h4 class=\"article-faq__question-title\">Is a T&amp;M contract good for the contractor?<\/h4><span class=\"article-faq__chevron\" aria-hidden=\"true\"><svg width=\"12\" height=\"8\" viewBox=\"0 0 12 8\" fill=\"none\" focusable=\"false\" aria-hidden=\"true\"><path d=\"M1 1.5L6 6.5L11 1.5\" stroke=\"currentColor\" stroke-width=\"1.5\" stroke-linecap=\"round\" stroke-linejoin=\"round\"><\/path><\/svg><\/span><\/summary><div class=\"article-faq__answer\">\n<p class=\"wp-block-paragraph\">It&#8217;s good for covering risk on unclear work, because you&#8217;re paid for every hour and purchase. It&#8217;s weaker for profit growth, because finishing faster means billing less. It also takes more paperwork and invites more questions from the client.<\/p>\n<\/div><\/details>\n\n\n\n<details class=\"wp-block-buildern-article-faq-item article-faq__item\"><summary class=\"article-faq__question\"><h4 class=\"article-faq__question-title\">Can I use T&amp;M for change orders on a fixed-price contract?<\/h4><span class=\"article-faq__chevron\" aria-hidden=\"true\"><svg width=\"12\" height=\"8\" viewBox=\"0 0 12 8\" fill=\"none\" focusable=\"false\" aria-hidden=\"true\"><path d=\"M1 1.5L6 6.5L11 1.5\" stroke=\"currentColor\" stroke-width=\"1.5\" stroke-linecap=\"round\" stroke-linejoin=\"round\"><\/path><\/svg><\/span><\/summary><div class=\"article-faq__answer\">\n<p class=\"wp-block-paragraph\">Yes, and it&#8217;s common. When extra work can&#8217;t be priced quickly, the contract can say that changes will be billed at the stated T&amp;M rates. Get a signed change order that authorizes the T&amp;M work, and an NTE amount if the client wants a limit.<\/p>\n<\/div><\/details>\n<\/div><\/section>\n","protected":false},"excerpt":{"rendered":"<p>A time and materials (T&amp;M) contract lets you bill the client for the hours your crew actually works at an agreed hourly rate, plus the materials you actually use with an agreed markup. You don&#8217;t commit to a total price up front, so the client carries the risk of the job growing and you&#8217;re paid [&hellip;]<\/p>\n","protected":false},"author":2,"featured_media":6670,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"content-type":"","_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":true,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_feature_clip_id":0,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_post_was_ever_published":false},"categories":[2,142],"tags":[],"class_list":["post-6625","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-blog","category-financial-management"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.8 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Time and Materials Contracts: Rates, Markup &amp; NTE Caps<\/title>\n<meta name=\"description\" content=\"When a time and materials contract fits, how to set labor rates and material markup, how not-to-exceed caps work, and how T&amp;M compares to cost-plus and fixed price.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Time and Materials Contracts: Rates, Markup &amp; NTE Caps\" \/>\n<meta property=\"og:description\" content=\"When a time and materials contract fits, how to set labor rates and material markup, how not-to-exceed caps work, and how T&amp;M compares to cost-plus and fixed price.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/\" \/>\n<meta property=\"og:site_name\" content=\"Buildern resources\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/buildernsoft\" \/>\n<meta property=\"article:published_time\" content=\"2026-11-27T14:05:21+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-11-27T14:05:22+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/11\/Time_and_Materials_Contracts_1460x952.png\" \/>\n\t<meta property=\"og:image:width\" content=\"1460\" \/>\n\t<meta property=\"og:image:height\" content=\"952\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Buildern Team\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Buildern Team\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"15 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/\"},\"author\":{\"name\":\"Buildern Team\",\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/#\\\/schema\\\/person\\\/c51d211aca7a0e50fd6cc6822f1801c0\"},\"headline\":\"Time and Materials Contracts: A Builder&#8217;s Guide to Rates, Markup and NTE Caps\",\"datePublished\":\"2026-11-27T14:05:21+00:00\",\"dateModified\":\"2026-11-27T14:05:22+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/\"},\"wordCount\":3204,\"publisher\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/buildern.com\\\/resources\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/Time_and_Materials_Contracts_1460x952.png\",\"articleSection\":[\"Construction Blog\",\"Construction Financial Management\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/\",\"url\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/\",\"name\":\"Time and Materials Contracts: Rates, Markup & NTE Caps\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/buildern.com\\\/resources\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/Time_and_Materials_Contracts_1460x952.png\",\"datePublished\":\"2026-11-27T14:05:21+00:00\",\"dateModified\":\"2026-11-27T14:05:22+00:00\",\"description\":\"When a time and materials contract fits, how to set labor rates and material markup, how not-to-exceed caps work, and how T&M compares to cost-plus and fixed price.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/#primaryimage\",\"url\":\"https:\\\/\\\/buildern.com\\\/resources\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/Time_and_Materials_Contracts_1460x952.png\",\"contentUrl\":\"https:\\\/\\\/buildern.com\\\/resources\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/Time_and_Materials_Contracts_1460x952.png\",\"width\":1460,\"height\":952,\"caption\":\"time and materials contracts\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/blog\\\/time-and-materials-contract\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/buildern.com\\\/resources\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Time and Materials Contracts: A Builder&#8217;s Guide to Rates, Markup and NTE Caps\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/#website\",\"url\":\"https:\\\/\\\/buildern.com\\\/resources\\\/\",\"name\":\"Buildern resources\",\"description\":\"Buildern resources\",\"publisher\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/buildern.com\\\/resources\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/#organization\",\"name\":\"Buildern resources\",\"url\":\"https:\\\/\\\/buildern.com\\\/resources\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/buildern.com\\\/resources\\\/wp-content\\\/uploads\\\/2021\\\/12\\\/Buildern-logo..png\",\"contentUrl\":\"https:\\\/\\\/buildern.com\\\/resources\\\/wp-content\\\/uploads\\\/2021\\\/12\\\/Buildern-logo..png\",\"width\":401,\"height\":137,\"caption\":\"Buildern resources\"},\"image\":{\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/buildernsoft\",\"https:\\\/\\\/www.instagram.com\\\/buildern.soft\\\/\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/buildern\\\/\",\"https:\\\/\\\/www.youtube.com\\\/@buildern\"]},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/buildern.com\\\/resources\\\/#\\\/schema\\\/person\\\/c51d211aca7a0e50fd6cc6822f1801c0\",\"name\":\"Buildern Team\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/3cac0fc1b73607901a65853ee2d1215c6a5516d31d72d65a8a0bc3fc8365db79?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/3cac0fc1b73607901a65853ee2d1215c6a5516d31d72d65a8a0bc3fc8365db79?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/3cac0fc1b73607901a65853ee2d1215c6a5516d31d72d65a8a0bc3fc8365db79?s=96&d=mm&r=g\",\"caption\":\"Buildern Team\"},\"sameAs\":[\"buildern\"],\"url\":\"https:\\\/\\\/buildern.com\\\/resources\\\/author\\\/buildern\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Time and Materials Contracts: Rates, Markup & NTE Caps","description":"When a time and materials contract fits, how to set labor rates and material markup, how not-to-exceed caps work, and how T&M compares to cost-plus and fixed price.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/","og_locale":"en_US","og_type":"article","og_title":"Time and Materials Contracts: Rates, Markup & NTE Caps","og_description":"When a time and materials contract fits, how to set labor rates and material markup, how not-to-exceed caps work, and how T&M compares to cost-plus and fixed price.","og_url":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/","og_site_name":"Buildern resources","article_publisher":"https:\/\/www.facebook.com\/buildernsoft","article_published_time":"2026-11-27T14:05:21+00:00","article_modified_time":"2026-11-27T14:05:22+00:00","og_image":[{"width":1460,"height":952,"url":"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/11\/Time_and_Materials_Contracts_1460x952.png","type":"image\/png"}],"author":"Buildern Team","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Buildern Team","Est. reading time":"15 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/#article","isPartOf":{"@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/"},"author":{"name":"Buildern Team","@id":"https:\/\/buildern.com\/resources\/#\/schema\/person\/c51d211aca7a0e50fd6cc6822f1801c0"},"headline":"Time and Materials Contracts: A Builder&#8217;s Guide to Rates, Markup and NTE Caps","datePublished":"2026-11-27T14:05:21+00:00","dateModified":"2026-11-27T14:05:22+00:00","mainEntityOfPage":{"@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/"},"wordCount":3204,"publisher":{"@id":"https:\/\/buildern.com\/resources\/#organization"},"image":{"@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/#primaryimage"},"thumbnailUrl":"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/11\/Time_and_Materials_Contracts_1460x952.png","articleSection":["Construction Blog","Construction Financial Management"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/","url":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/","name":"Time and Materials Contracts: Rates, Markup & NTE Caps","isPartOf":{"@id":"https:\/\/buildern.com\/resources\/#website"},"primaryImageOfPage":{"@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/#primaryimage"},"image":{"@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/#primaryimage"},"thumbnailUrl":"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/11\/Time_and_Materials_Contracts_1460x952.png","datePublished":"2026-11-27T14:05:21+00:00","dateModified":"2026-11-27T14:05:22+00:00","description":"When a time and materials contract fits, how to set labor rates and material markup, how not-to-exceed caps work, and how T&M compares to cost-plus and fixed price.","breadcrumb":{"@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/#primaryimage","url":"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/11\/Time_and_Materials_Contracts_1460x952.png","contentUrl":"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/11\/Time_and_Materials_Contracts_1460x952.png","width":1460,"height":952,"caption":"time and materials contracts"},{"@type":"BreadcrumbList","@id":"https:\/\/buildern.com\/resources\/blog\/time-and-materials-contract\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/buildern.com\/resources\/"},{"@type":"ListItem","position":2,"name":"Time and Materials Contracts: A Builder&#8217;s Guide to Rates, Markup and NTE Caps"}]},{"@type":"WebSite","@id":"https:\/\/buildern.com\/resources\/#website","url":"https:\/\/buildern.com\/resources\/","name":"Buildern resources","description":"Buildern resources","publisher":{"@id":"https:\/\/buildern.com\/resources\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/buildern.com\/resources\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/buildern.com\/resources\/#organization","name":"Buildern resources","url":"https:\/\/buildern.com\/resources\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/buildern.com\/resources\/#\/schema\/logo\/image\/","url":"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2021\/12\/Buildern-logo..png","contentUrl":"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2021\/12\/Buildern-logo..png","width":401,"height":137,"caption":"Buildern resources"},"image":{"@id":"https:\/\/buildern.com\/resources\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/buildernsoft","https:\/\/www.instagram.com\/buildern.soft\/","https:\/\/www.linkedin.com\/company\/buildern\/","https:\/\/www.youtube.com\/@buildern"]},{"@type":"Person","@id":"https:\/\/buildern.com\/resources\/#\/schema\/person\/c51d211aca7a0e50fd6cc6822f1801c0","name":"Buildern Team","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/3cac0fc1b73607901a65853ee2d1215c6a5516d31d72d65a8a0bc3fc8365db79?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/3cac0fc1b73607901a65853ee2d1215c6a5516d31d72d65a8a0bc3fc8365db79?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/3cac0fc1b73607901a65853ee2d1215c6a5516d31d72d65a8a0bc3fc8365db79?s=96&d=mm&r=g","caption":"Buildern Team"},"sameAs":["buildern"],"url":"https:\/\/buildern.com\/resources\/author\/buildern\/"}]}},"jetpack_sharing_enabled":true,"jetpack_featured_media_url":"https:\/\/buildern.com\/resources\/wp-content\/uploads\/2026\/11\/Time_and_Materials_Contracts_1460x952.png","post_mailing_queue_ids":[],"_links":{"self":[{"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/posts\/6625","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/comments?post=6625"}],"version-history":[{"count":4,"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/posts\/6625\/revisions"}],"predecessor-version":[{"id":6671,"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/posts\/6625\/revisions\/6671"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/media\/6670"}],"wp:attachment":[{"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/media?parent=6625"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/categories?post=6625"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/buildern.com\/resources\/wp-json\/wp\/v2\/tags?post=6625"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}